Case study
LTI Metaltech, Milton Park
A twin-boiler installation designed to fit the plant room while the offices stayed open

Commercial boiler replacement
Project brief
LTI Metaltech’s facilities manager approached the Oxyplumb Commercial team directly to replace the existing floor-standing boilers and flue at the company’s Milton Park premises.
Designed around the plant room
Space constraints ruled out a standard arrangement. The Oxyplumb Commercial team built a custom cascade frame for two Vaillant ecoTEC Plus 64 kW commercial boilers.
- Reverse-return configuration for optimum performance.
- Plate heat exchanger for hydraulic separation from the existing heating system.
- Cascaded flue routed through the existing flue opening, avoiding new roof work or a new roof penetration.
Installation and commissioning
The team completed the necessary wiring alterations. The existing heating system was flushed and dosed with inhibitor before the completed installation was fully tested.
Live office coordination
The offices remained operational throughout. The Oxyplumb Commercial team worked around LTI Metaltech’s schedule, kept work areas clean and tidy, and maintained safe access routes.
Completed result
The finished installation is a compact, purpose-built cascade combining two 64 kW Vaillant boilers, the custom support frame, reverse-return pipework, hydraulic separation and the cascaded flue through the existing opening.
Project photographs
Before
Installation and testing
Completed views
COMMERCIAL HEATING, GAS & PLUMBING
Planning work at your premises?
Tell the Oxyplumb Commercial team what you would like to improve. We can help you work through the options and plan the next step.
Support for a similar commercial project
Planning something similar? We can talk through what you need and how we could help. These services are a useful place to start.
Discuss your project